Production Schedule

Pre Pitch- general research, specified research, pattern designers, make headings/patterns gather images and resources, create wireframes

Pitch- 11th March

Week of the 18th March-
  • Finish organizing resources
  • Make any suggested changes brought up in the Pitch
  • ensure that blog is fully up to date
  • (Sues work also)

Week of the 25th March

  • Start investigating Ibooks
  • Look at some interactive examples of the Ibook and continue blog
  • Begin building backgrounds for Ibook

Easter Holidays 1st April to 15th-

  • Work on Ibook
  • Get all of my content into the Ibook- doesn’t have to be interactive at this point but want a basis to work from so that interactivity can be added at a later point
  • Gather sources for Sue
  • Continue blog
  • Generate some cleaner wireframes with labels

Week Beginning 15th April-

  • Finish Ibook and corresponding blog
  • Make sure Ibook is interactive
  • Tidy sketchbook

Week Beginning 22nd April to end of the week beginning the 29th April-

  • Work on Website
  • Continue basic website
  • Write Sues essay


Week beginning 6th of May end of the week beginning 13th May-

  • Ensure website is responsive (ask George)
  • Put Videos and images into Website 
  • Experiment with css tricks
  • Blog

Week beginning 20th May-
  • Crit
  • Finishing touches
  • Evaluation
  • Hand in Final essay for Sue